The Move Continues

 
Next

A very careful loading of the reformer. 

The second and third truckloads are staged for loading.

The externally heated pyrolysis system shell with outboard bearings was loaded. The stainless steel auger is only 6 feet (182 cm) long. Software manages the heating rates to insure auger alignment. 

A setback.  The heaters on the upper portion of the reformer are damaged during unloading at UGA.  An inspection reveals they will have to be removed and repaired.

The damage is minor and will not set us back too much. 

It was only a few days later we also found out that in severe weather, strong winds can blow rain under the shed.  Everything is going to have to be weather proofed.

 